<< Click to Display Table of Contents >> Navigation: Project > Stages |
The Stages tab offers a graphic overview of particular project stages. You can also add or remove activities for each stage, as well as change their status.
1)Module Toolbar: For more information, see Project → Functions & Processes → Basic Project Functions.
2)Stages: Stages (activity groups) can be added in the tab Project/Activities → sub-tab Details. Each stage represents a group of various activities (3).
3)Activities: Activities can be inserted directly from this tab or tab Project/Activities.
Note: Each stage or activity is technically a criterion. Criteria can be created and managed via Administration → General → Products → Criteria structure. |
Stage end date: The stage end date represents the end date of the last activity belonging to the stage. The end date can be defined in Project/Activities.
4)Right-click context menu. Appears when an activity is selected.
Add activity: Insert an activity.
Delete activity: Delete selected activity.
Not started/Ongoing/On-hold/Done/Completed: Change the status of the activity. The color of the box will change accordingly. The status which is currently selected will be greyed out in the context menu.
5)Right-click on a stage to associate it with another activity.